Curriculum Management Timescales and Updates
The current timescales for the Curriculum Management Project:
- Akari System Discovery Workshops November–December 2020,
- Review Discovery Report January 2021.
- Design and Planning February 2021–July2021
- Implementation July 2021–September2022.
- Testing and Pilot September 2022 -December 2022
- Launch January 2023
Some of the key achievements and milestones delivered to date are listed below:
- Initial system configuration complete (confirmation of data required and functionality required)
- Migration templates created
- Baseline data for modules and provision (programmes and courses)
- Cleanse of current provision, module, and availability data
- One third of migration templates to be populated complete
- Creation of 9 workflows (processes) in system for testing (Module, Provision Approval/Change/Close and Administrative processes)
- Integrated business case, module and provision set up tasks
- Baseline and set up of accreditation bodies
- Initial extraction of test data successful and SITS integration in development
- Version Comparison report configured
- Advanced Search configured
- Approval of two new roles created to manage, support, and develop Curriculum Management